| Actual ACWP
BAC
Baseline
BCWP
BCWS
Crashing the Critical Path
Critical Path
Current
CV
Free Slack
Lag Time
Lead Time
Pert Chart
Resource Overallocation
Slack
SV
Total Slack
|
List of commonly used terms in MS Project and Project Management
- Actual
- Data related to actual achievements (percent completed), cost, resource use etc. Tasks
containing actual data are either finished or have at least started. See also: Baseline, Current
- ACWP
- Term from earned value analysis.
The Actual Cost of Work Performed (ACWP) shows the cost involved achieving the current
status of completion. See also: BAC, CV, Controlling.
- BAC
- Term from earned value analysis.
The Budgeted At Completion (BAC, a.k.a. baseline cost) is the cost of a certain project or
task as it was planned and scheduled in the baseline. See also ACWP,
CV, Controlling.
- Baseline
- Fixed model of how the project is supposed to go, a.k.a. Planned Information. This
information once saved never changes. It is the plan all changes are compared to. See
also: Actual, Current
- BCWP
- Term from the earned value analysis.
- The Budgeted Cost of Work Performed (BCWP, a.k.a. earned value) is the actually
completed percentage for a certain date times the baseline cost. See also: BCWS, SV, Controlling.
- BCWS
- Term from the earned value analysis.
- The Budgeted Cost of Work Scheduled (BCWS, a.k.a. planned earned value)
is the planned percentual completion of a task for a certain date, times the total cost
according to the baseline. See also: BCWP, SV, Controlling.
- Crashing the Critical Path
- Also known as reducing the duration of the critical path. There are several ways to do
that:
- Changing the task relationships: Eliminate unnecessary dependencies or predecessors,
Overlapping tasks partially, rearrange the order of tasks.
- Scheduling overtime: The most obvious solution, but not necessarily the best. This is
done by changing the Resource Calendar.
- Adding more resources: May not be possible, causes extra costs.
- Critical Path
- Method to determine the critical tasks based on relationships, duration and resource
availability. If any of the critical tasks is delayed the whole project will be delayed.
See also: Crashing the Critical Path
- Current
- The current data reflects changes made during the project on tasks that have not started
yet. This usually happens if you gain better insights into a task while the project is
running or accommodate for external changes (for example a supplier suddenly charges more
money for his goods.) See also: Actual, Baseline
- CV
- Term from earned value analysis.
The (earned value) cost variance is the difference between BAC and ACWP. It is shows if
the project or task is on track with respect of its cost. See also: SV, Controlling..
- Free Slack
- Free slack is the amount of time a task can slip before it delays another task.
- Lag Time (a.k.a. delay, gap)
- Task two starts delayed after Task 1 ends in a controlled manner. A lag time is
expressed by a positive (+) sign in MS Project. The values can have all duration labels
from the duration table or can be a
percentage (%).
- Lead Time (a.k.a. overlap)
- Task two starts before Task 1 ends in a controlled manner. A lead time is expressed by a
negative (-) sign in MS Project. Units can have all duration labels from the duration table or can be a percentage (%).
- Pert Chart
- Also known as Network Chart. Graphical method to show task connections and
relationships.
- Resource over-allocation
- Resource over-allocation occurs when a resource is scheduled for more hours of work than
are available in the resource calendar at a given time. Therefore, you must either
reschedule the task for a time when the resource is available or reallocate the resource's
work on various tasks.
- Slack (a.k.a. float time)
- Slack is the amount of time a task can slip before it affects another task's dates or
the project finish date. Slack is sometimes referred to as float time.
- Slack is shown in the resource allocation view and is therefore very helpful to adjust
the schedule manually without causing changes in the overall schedule.
In MS Project, if the total slack is negative, the duration for a task is too long for its
successor to begin on the date required by its constraint.
See also: Total Slack, Free Slack
- SV
- Term from earned value analysis.
- The (earned value) schedule variance (SV) is the difference between BCWP and BCWS. This
value can be used to determine if the project or task is on track with respect to its
progress. See also CV, Controlling.
- Total Slack
- Total slack is the amount of time a task can slip before it delays the project finish
date.
|